The launch pad during the NG-3 flight, November 13, 2025.
© Blue Origin
The challenge of returning to flight for the New Glenn
Critical infrastructure spared
Despite the force of the explosion , the components with the longest manufacturing lead times were unaffected . Dave Limp, CEO of Blue Origin, shared a detailed assessment after inspecting the facilities. ” The propellant storage park, oxygen, liquid hydrogen, and LNG (liquefied natural gas) tanks are all in good condition ,” he reassured on his Twitter account and in a press release. ” This is fortunate because these are items with very long lead times. The water tower is also in good condition . The large support tower is damaged, but it can be repaired on-site rather than being demolished and replaced .” All of this allows the company to maintain its ambitious goals. ” We will be flying again before the end of this year ,” he concluded optimistically.